In an implementation plan, what do dependencies describe?

Tasks that have no relation to other activities.

Tasks that cannot proceed until another task is completed.

Dependencies describe the relationships that determine the sequence of work in an implementation plan. When one task can’t start until another finishes, that relationship is a dependency. Recognizing these linkages lets you schedule tasks accurately, set realistic timelines, and understand how delays affect the rest of the plan. This isn’t about tasks that stand alone, nor about budget approvals or training requirements by themselves. For example, you typically must finish system design before coding can begin, because coding depends on the design being complete.

Budget items that must be approved by auditors.

Staff training requirements only.

Next question

Find the option that is right for you!

All options are one-time payments.

$12.50

30 day premium pass

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
👑$30.00 $87.50 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $87.50 usd value for $30.00! You save $57.50!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$12.50 $18.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy